Service Contacts: USA, Canada & Caribbean | Mexico | Central & South America | Europe, Africa, Middle East, Asia, Pacific |
Printer-Friendly Version

Engineering Design Tops List of NEC's Comprehensive Generator Services

NEC design engineers are ready to respond to any generator design issue that may arise during a generator repair or retrofit project. While the individual backgrounds of our engineers may vary, many began their careers at OEMs or worked for major utilities before coming to NEC, or both. This diversity of knowledge and experience gives our design team a wide-ranging base of experience with generating units of all ages, makes, sizes and types. Along with the winding design, our engineers address related issues of unit reliability, efficiency, maintainability and longevity. They also are involved in the design, development, evaluation and testing of semi-conducting coatings, varnishes and tapes for electrical field grading in the end-windings of high voltage stators.

Past projects have Involved generator rewinds, uprates or repairs to rotating electrical equipment manufactured by nearly every supplier in the world. A partial list includes General Electric, Westinghouse, Siemens, Allis Chalmers, Electric Machinery, NS Peebles, Brush, Elliott, Alstom, English Electric, Reliance, Toshiba, Hitachi, GEC, Mitsubishi and ABB. These projects have services turbogenerators, hydrogenerators, AC and DC motors, exciters, frequency changes and synchronous condensers. Sizes have ranged from motors of a couple thousand horsepower, to 1000 MVA generators.

In addition to complete uprates, including rewinds of both the rotors and stators, specific engineering tasks have included thermal analysis of complete generators, field winding thermal analysis, redesign of field windings to improve thermal performance, fan design, stator winding vibration analysis and testing, stator core vibration analysis and testing, electromagnetic force analysis, rotor component stress analysis, rotor and retaining rings specifications, and rewind specifications.

The following is a short explanation of the engineering tasks most common with the typical generator project:

  1. Uprate Studies done to determine what can be done to increase the output capability. These studies analyze the electrical, magnetic, mechanical and ventilation aspects of the generator in order to determine best combination of design parameters to meet output requirements.

  2. Life Extension Studies based on inspection, non-destructive testing and analyses that:

    Estimate for the unit's remaining life

    Identify what actions needed to extend the overall machine life or the time until a possible failure

    Guide the development of a maintenance plan that maximizes unit reliability and availability

  3. Studies that address specific performance issues such as:

    Noise Reduction – for generator designs that are susceptible to slot passing frequency noise or other harmonics

    Reduction of Vibration due to intermodulation effect of magnetic circuits

    Optimum Eddy Current Loss Reduction schemes

    Effects of Changes – insulation and ventilation schemes, including calculation of steady state and transient temperatures of all components

    Heating and Ventilation studies – evaluate existing schemes or to achieve improvements in friction and windage losses, reduction in hot spots, and general improvement in machine temperature.

    Theoretical modeling and analysis of Generator Reliability

  4. Failure Analysis performed prior to any repairs – analyses include recommendations to mitigate the possibility of a similar failure on another machine, or a reoccurrence of the same failure.

  5. Re-Engineering Design performed, as necessary. Our advanced proprietary design software assures the compatibility of replacement components, so that replacement parts are equal or better in quality and performance to the originals. Features include but are not limited to:
  • CAD/CAM design and element analysis
  • Full electromagnetic calculations for all sizes and types of units
  • Calculations of estimated machine characteristics from physical dimensions
  • Calculation of performances, parameters, losses and the efficiency of the entire size range of fossil, hydro, and nuclear generators
  • Specialized tooling design, such as tooling for large high voltage stator coils to fit into skewed stator cores

Typical Project Experience

NEC's team has been directly involved in hundreds of projects directly related to specific engineering problems with large generators and motors. A sampling of recent projects are listed below:

Turbogenerator Projects

  • Failure analysis of water-cooled stator windings (TIL 1098)
  • Analysis, redesign and manufacture of rotor fan blades to reduce blade failure (multiple projects)
  • Retaining ring changeouts to upgrade retaining rings from non-magnetic18Mn5Cr to 18Mn18Cr rings. (TIL 1097-3 and OMM 089) (multiple projects)
  • Forging and retaining ring modifications to repair rotor tooth top cracking (TIL 1292 and OMM 103) (multiple projects)
  • Analysis, redesign and manufacture of winding and rewind of generator unit that had experienced two previous in-service failures prior to NEC involvement
  • Clean, inspect, test and repaint winding during routine outage (multiple projects)
  • Manufacture replacement stator winding and rewind unit on expedited schedule (multiple units)
  • Complete emergency stator core inspection and stator rewind in 19 days
  • Joint effort with partners to rewind both the stator and the rotor of an inner-water-cooled generator. NEC manufactured both stator and rotor windings. Stator rewind was complete in 20 days.
  • Following a stator hydrogen cooler valve failure, a generator overheated and experienced thermal instability over the generator field at full load. This melted all soldered stator bar connections. Rotor was rewound and stator bar connections resoldered.
  • Strip global VPI stator, clean and test stator core, rewind stator (multiple units)
  • Stator and rotor winding manufacture for OEM for use in its own rewind projects (multiple)
  • Stator and rotor winding manufacture for NEC partner for use its own projects or in joint projects (multiple projects for multiple partners)
  • Manufacture and install new winding in 42 days; including redesign of "original" winding design to eliminate partial discharge problem caused by absence of side filler packing material
  • Strip WESTAC generator stator and clean and test the stator core. remove, reinsulate and reinstall existing bus rings, surge rings, and support brackets. Remove, repair and restack stator core. Furnish and install stator winding with RTDs
  • Design, manufacture and install new stator winding that eliminates lead group transposition to provide maximum upratabe potential. Also provided new enhanced bus rings
  • Rewedge stator (multiple projects)
  • Rewind and restack four-pole generator stator on-site and concurrently repair and reinsulate rotor poles and remount them to rotor off-site in NEC's Service facility
  • Rewind and partial restack, including replacement of all through bolts with new nitronic type bolts
  • Refurbish damaged 20-year-old spare winding
  • Refurbishment and reinstallation of aluminum rotor windings (multiple projects)
  • Refurbishment and reinstallation with improved adhesives of rotor windings experiencing turn insulation migration (TIL 1308-2R2) (multiple projects)
  • Repairs and rewind of rotor experiencing turn to turn shorts and/or thermal imbalance (TIL 1143-3 and TIL 1158-3) (multiple projects)
  • Repairs and refurbishment of collector rings and journals
  • Redesign and repair of rotor leads and pole crossover connectors to eliminate cracking (AIB 8004 and AIB 8306) (multiple projects)
  • Refurbishment of large, inner-hydrogen-cooled brushless exciter
  • Refurbishment of various brushless exciters (AIB 8205) (multiple projects)

Hydrogenerator Projects

  • Bulb generator stator core failure analysis
  • Spider thrust bearing failure analysis
  • Thrust bearing load capacity study
  • Spider stress analysis
  • Analysis of rotor spring key migration
  • Field winding analysis
  • Finite element analysis of failed damper bars
  • Guide bearing failure analysis
  • Ventilation analysis
  • Thermal analyses
  • Armature winding corona analysis
  • 50-year and other generator life extension analyses
  • Inspect 1920 vintage generator, advise of suitability for continued use
  • Excessive slip ring brush wear
  • Noise reduction analysis
  • Determination of cause of high temperature and vibration at core splits for pumped storage unit
  • Determination of cause of excessive stator core vibration in generator unit
  • Pole density calculations
  • Oil lift panel redesign
  • Redesign of field pole connectors
  • Redesign rotor rim
  • Re-design thrust bearing cooling oil system
  • Blower blade re-design for ventilation upgrade
  • Redesign hydrogenerator to change the number of coolers
  • Design of new field poles (convert from cast iron to laminated)
  • Design new sound proof housing
  • Design new housings, coolers, fans, etc., to convert open ventilation system to closed system
  • Where a stator failed to ground, partial rewind and rewedge of stator, and cleaning and testing of rotor.
  • Uprate of generator, providing and installing stator coils, new bus rings, and new stator core and clamping structure (multiple projects)
  • Manufacture, installation and testing for new armature winding, new bus rings, spare coils or winding (multiple projects)
  • Manufacture and installation of windings for 11 units at two plants; nine units made at same rating by by three different OEMs, Mitsubishi, AEG and BBC and two units made by Rade Koncar a different rating
  • Manufacture and installation of new stator winding and new stator core, plus re-rounding of the core (multiple projects)
  • Frequency change of 12 units: Installation of uprated windings and redesign and configuration of rotors for additional poles and manufacture of all new pole pieces
  • Stator rewind and uprate plus extensive work on core, frame and fingerplates to repair damage
  • Re-plumbing of generator/turbine shaft, redrilling of stator frame and fabrication of new dowels for stator frame and upper bridge to round out the stator frame
  • Replacement of the generator cooling piping
  • Installation of a PDA coupler systems

Exciter Projects

  • Refurbishment, including armature rewind, of a 4500 kW, 525 Volts, 8575 Amperes, 3600 rpm hydrogen-cooled brushless exciter. This exciter had a total of 144 diodes, with 24 diodes in parallel per phase per polarity, and 72 capacitors and 72 fuses. It is only one of a handful
    of hydrogen-cooled exciters
  • Repairs to a hydrogenertor stator's main and pilot exciters

Motor Projects

  • Multiple projects involving the full analysis and redesign of squirrel cage induction motors, changing of bar profiles to change speed-torque characteristics and speed, and to increase fatigue life

Capabilities for Turbogenerators

Stators

  • Testing, inspections and life assessments
  • Stator rewinds
  • Core restacks and repairs, Partial or Complete
  • Parallel ring modfications
  • Main-Neutral Interchanges
  • Stator winding end turn support modifications
  • Rewedges, wedge tightening
  • Through bolt retightening and hardware replacements; through bolt replacements
  • Field testing of large generators for confirmation of performance parameters
  • Full redesign of generator stator core technology and execution of on-site or in-shop restacking after catastrophic failure or just for improvement of machine performance.
  • Analysis of stator frame structure and measures for eliminating deficiencies

Rotors

  • Testing, inspections and life assessments
  • Collector Ring Machining
  • Fan Repairs/Replacement
  • Radial lead stud replacement
  • Slot Wedge replacment
  • Supply or repair magnetic or non-magnetic retaining rings
  • Rotor tooth top cracking repair
  • Calculations to determine the proper shrink fits on all removable parts on generator rotors including, but not limited to, retraining rings, fans, couplings and hubs.
  • Calculations involving stress, flexure, fatigue, and fracture mechanics necessary to select the appropriate materials for replacement retaining rings, fans, couplings, hubs, keys, wedges, lead bars and lead studs.
  • Static electrical testing of generator rotors.
  • Evaluation and determination of fatigue life with regard to crack initiation and propagation in the tooth structure of high-speed generator rotors.  Redesign of the tooth structure to reduce and/or eliminate the susceptibility of future cracking
  • Retaining Ring Modifications, Short or Long Types
  • Leak Testing & Modification of Rotor Radial Lead Assemblies
  • Field Crossover Replacements
  • Improvements to Enhance Vibration Stability
  • Design and implementation of the direct cooling system of the rotor winding end turns to reduce the coil temperature to improve the reliability or increase the machine output.
  • Testing – winding resistance, impedance, insulation resistance, polarization index, high potential, electrical tests at running speed including flux probe.
  • Replacement of end turn blocking.
  • Replacement, repair, reinsulation of individual turns of coils.
  • Removal, cleaning and reinsulation of existing copper winding.
  • Manufacturing new coils using OFHC silver-bearing copper.
  • New slot liners and insulating materials.
  • Main leads, studs and stud seals.
  • Replacement retaining rigs, slot wedges, fans.
  • Collector ring repair or replacement.
  • Redesign to eliminate problems.
  • Complete rewind of rotor.
  • Dynamic balancing of rotor at rated speed plus momentary 10% overspeed.
  • Manufacturing of complete new rotor
  • Vibration analysis of high-speed flexible generator rotors at all dynamic mode shapes, two and three bearing machines
  • Dimensional checking of generator rotor components and calculations to determine proper interference fits

Capabilities for Hydrogenerators

Stators

  • Testing, inspections and life assessments
  • Stator Rewinds
  • Core Restacks and Repairs, Partial or Complete
  • Parallel Ring Modfications
  • Main-Neutral Interchanges
  • Rewedges, Wedge Tightening
  • Through Bolt Retightening & Hardware Replacements
  • Calculation of performances, parameters, losses and the efficiency of the entire size range of hydrogenerators
  • Heating and ventilation studies to evaluate existing schemes or to achieve improvements in friction and windage losses, reduction in hot spots, and general improvement in machine temperature.
  • Field testing of large generators for confirmation of performance parameters
  • Full redesign of turbo/hydro generator stator core technology and execution of on-site or in-shop restacking after catastrophic failure or just for improvement of machine performance.
  • Analysis of stator frame structure and measures for eliminating deficiencies.
  • Theoretical calculations for rotor winding temperature change due to change in rotor coil insulation.
  • Calculations of stresses at normal and run-a-way speeds for hydrogenerators.
  • Full redesign of generator stator core technology and execution of on-site or in-shop restacking after catastrophic failure or just for improvement of machine performance.
  • Analysis of stator frame structure and measures for eliminating deficiencies

Rotors

  • Testing, inspections and life assessments
  • Spider repairs and requalifications
  • Field Pole repairs, refurbments or replacement with new
  • Testing – winding resistance, insulation resistance, pole drop, high potential
  • New pole pieces and pole keys
  • New revolving field coils – wire wound, edge bent or fabricated.
  • Collector rings, fans, ventilation.
  • Bearing repairs.
  • Manufacturing and NDE of rim and spider.
  • Frequency conversion projects.
  • Redesign of hydrogenerator spider, pole pieces and field winding to improve/change machine performance.
  • Mechanical non-destructive examination of generator rotor components and shaft forgings.
  • Dimensional checking of generator rotor components and calculations to determine proper interference fits.
  • Improvements of design and performance of pole-pole field winding connections of salient pole synchronous machines.

Capabilities for Exciters

  • Inspect, test and clean
  • Fuse and diode replacement
  • Repair or replace glass banding
  • Skid refurbishment
  • TC replacement
  • Rewind

READ MORE about NEC's exciter services.

Capabilities for High-Voltage Motors

Squirrel Cage Induction Motors

READ MORE about NEC's services for squirrel cage rotors.

RETURN to top of this page.

 

About Us || Site Map || Privacy Policy || Contact Us || ©2006 NATIONAL ELECTRIC COIL® All Rights Reserved